1. Exhibition Hall 30% Design Document Update
Larry Barton from Strang presented to the committee on the progress of
the design development phase
Contracted for April - October - 6 month design progress
Barton provided an update on the 30% design development
Barton provided an overview of the sustainable elements of the project
Barton indicated that 2025 is for design development, 2026 for
construction documents and bidding, 2027 to start construction, with
construction complete 2030-2031
Discussion ensued regarding sustainability features.
Discussion ensued about how the process was going and if Strang needs
anything from the committee. Barton indicated they do not unless the
committee has something for them.
Discussion ensued regarding coordination between multiple projects at the
same time.
Strang noted that they are aware of the master plan, will need to react when
the timelines are clearer
Scheibler noted the plan is to keep operations while the redevelopment is
taking place
Questions about stormwater management, traffic, and parking. Barton
indicated that is in process.
Discussion ensued regarding the timeline.
AEC EXHIBITION HALL 30% DESIGN DOCUMENT UPDATE - STRANG, INC.
E. Reports to Committee
1. Chair's Update
a. Update on June 12, 2025 County Board Committee of the Whole
Erickson provided an update on the COW including the tour, Potter Lawson
drawings, COW meeting
Issues brought up by Supervisors include housing, if a public/private
partnership would create a monopoly, will continue to have opportunities for
supervisors to talk with Kevin
Scheibler added that there were a lot of thoughtful questions about how to
move forward