CONTRACT CHANGE ORDER #23-DANE COUNTY SHERIFF'S SE
PRECINCT-125 VETERAN'S ROAD, STOUGHTON, WI-CONTRACTOR:
U.S. VET GENERAL CONTRACTING, LLC.
A motion was made by DeGARMO, seconded by RIPP, that the Action Item be
approved. The motion carried by a voice vote (5-0; YGP: 2-0).
Todd Draper spoke on this agenda item.
CONTRACT CHANGE ORDER #24-DANE COUNTY SHERIFF'S SE
PRECINCT-125 VETERAN'S ROAD, STOUGHTON, WI-CONTRACTOR:
U.S. VET GENERAL CONTRACTING, LLC.
A motion was made by DeGARMO, seconded by RIPP, that the Action Item be
approved. The motion carried by a voice vote (5-0; YGP: 2-0).
Todd Draper spoke on this agenda item.
CONTRACT CHANGE ORDER #2-EMERGENCY MANAGEMENT
BUILDING-FACILITY REMODEL-5415 KING JAMES WAY, FITCHBURG,
WI-CONTRACTOR: FOXARNESON, INC.
A motion was made by DeGARMO, seconded by RIPP, that the Action Item be
approved. The motion carried by a voice vote (5-0; YGP: 2-0).
Todd Draper spoke on this agenda item.
CONTRACT CHANGE ORDER #3-EMERGENCY MANAGEMENT
BUILDING-FACILITY REMODEL-5415 KING JAMES WAY, FITCHBURG,
WI-CONTRACTOR: FOXARNESON, INC.
A motion was made by DeGARMO, seconded by RIPP, that the Action Item be
approved. The motion carried by a voice vote (5-0; YGP: 2-0).
Todd Draper spoke on this agenda item.
CONTRACT CHANGE ORDER #4-EMERGENCY MANAGEMENT
BUILDING-FACILITY REMODEL-5415 KING JAMES WAY, FITCHBURG,
WI-CONTRACTOR: FOXARNESON, INC.
A motion was made by DeGARMO, seconded by RIPP, that the Action Item be
approved. The motion carried by a voice vote (5-0; YGP: 2-0).
Todd Draper spoke on this agenda item.