| 1 | 2 | | Fund Transfer | INCREASE CAPITAL CULVERT REPLACEMENT FUNDS | approved | Pass |
Action details
|
Not available
|
2016 RES-056
| 1 | | | Resolution | AWARD OF CONTRACT FOR HENRY VILAS ZOO - ADMINISTRATION BUILDING REROOFING AND RECLADDING | Sub. 1 to the resolution be recommended for approval as amended | Pass |
Action details
|
Not available
|
2016 RES-057
| 1 | | | Resolution | AUTHORIZATION TO INCREASE CHANGE FUNDS FOR THE DANE COUNTY LANDFILL | recommended for approval | Pass |
Action details
|
Not available
|
2016 RES-058
| 1 | | | Resolution Requiring 2/3rds Vote | AWARD OF CONTRACT FOR OFFICE OF EQUITY AND INCLUSION - CITY COUNTY BUILDING 3RD FLOOR | recommended for approval | Pass |
Action details
|
Not available
|
2016 ACT-090
| 1 | | | Action Item | CONTRACT CHANGE ORDER #5 - NORTHPORT NURSES DORM DECONSTRUCTION | approved | Pass |
Action details
|
Not available
|
2016 ACT-091
| 1 | | | Action Item | CONTRACT CHANGE ORDER #4 - NORTHPORT NURSES DORM DECONSTRUCTION | approved | Pass |
Action details
|
Not available
|
2016 ACT-093
| 1 | | | Action Item | CONTRACT CHANGED ORDER #3 - MEDICAL EXAMINER OFFICE BUILDING | approved | Pass |
Action details
|
Not available
|
2016 ACT-094
| 1 | | | Action Item | CONTRACT CHANGE ORDER #4 - MEDICAL EXAMINER OFFICE BUILDING | approved | Pass |
Action details
|
Not available
|
2016 ACT-095
| 1 | | | Action Item | CONTRACT CHANGE ORDER #5 - MEDICAL EXAMINER OFFICE BUILDING | approved | Pass |
Action details
|
Not available
|
2016 ACT-096
| 1 | | | Action Item | CONTRACT CHANGE ORDER #6 - MEDICAL EXAMINER OFFICE BUILDING | approved | Pass |
Action details
|
Not available
|
2016 ACT-097
| 1 | | | Action Item | CONTRACT CHANGE ORDER #26 - CONSTRUCTION OF C&D MATERIAL RECOVERY FACILITY AT DANE COUNTY LANDFILL SITE #2 | approved | Pass |
Action details
|
Not available
|
2016 ACT-098
| 1 | | | Action Item | CONTRACT CHANGE ORDER #27 - CONSTRUCTION OF C&D MATERIAL RECOVERY FACILITY AT DANE COUNTY LANDFILL SITE #2 | approved | Pass |
Action details
|
Not available
|
2016 ACT-099
| 1 | | | Action Item | CONTRACT CHANGE ORDER #28 - CONSTRUCTION OF C&D MATERIAL RECOVERY FACILITY AT DANE COUNTY LANDFILL SITE #2 | approved | Pass |
Action details
|
Not available
|
2016 ACT-100
| 1 | | | Action Item | CONTRACT CHANGE ORDER #29 - CONSTRUCTION OF C&D MATERIAL RECOVERY FACILITY AT DANE COUNTY LANDFILL SITE #2 | approved | Pass |
Action details
|
Not available
|
2016 ACT-101
| 1 | | | Action Item | CONTRACT CHANGE ORDER #30 - CONSTRUCTION OF C&D MATERIAL RECOVERY FACILITY AT DANE COUNTY LANDFILL SITE #2 | approved | Pass |
Action details
|
Not available
|
2016 ACT-102
| 1 | | | Action Item | CONTRACT CHANGE ORDER #33 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-103
| 1 | | | Action Item | CONTRACT CHANGE ORDER #34 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-104
| 1 | | | Action Item | CONTRACT CHANGE ORDER #35 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-105
| 1 | | | Action Item | CONTRACT CHANGE ORDER #36 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-106
| 1 | | | Action Item | CONTRACT CHANGE ORDER #37 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-107
| 1 | | | Action Item | CONTRACT CHANGE ORDER #38 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|
Not available
|
2016 ACT-108
| 1 | | | Action Item | CONTRACT CHANGE ORDER #39 - CONSTRUCTION OF EAST HIGHWAY GARAGE | approved | Pass |
Action details
|