2017 MIN-396
| 1 | 1. | | Minutes | MINUTES FROM THE NOVEMBER 14TH, 2017 PUBLIC WORKS & TRANSPORTATION COMMITTEE | approved | Pass |
Action details
|
Not available
|
2017 FTR-31
| 1 | 1. | | Fund Transfer | FUND TRANSFER REQUEST FOR THE LANDFILL SITE #2 (RODEFELD) | approved | Pass |
Action details
|
Not available
|
2017 RES-316
| 1 | 1. | | Resolution | AWARD OF CONTRACT FOR: NEW RESTROOM FACILITY AT THE HENRY VILAS ZOO | sub. 1 to the resolution be recommended for approval | Pass |
Action details
|
Not available
|
2017 RES-323
| 1 | 2. | | Resolution | ADDENDUM AGREEMENT NO. 1 FOR CONSTRUCTION AND DEMOLITION WASTE RECYCLING SERVICES AT THE DANE COUNTY LANDFILL SITE | recommended for approval | Pass |
Action details
|
Not available
|
2017 RES-331
| 1 | 3. | | Resolution | AWARD OF CONTRACT FOR ENVIRONMENTAL MONITORING AT THREE DANE COUNTY LANDFILLS | recommended for approval | Pass |
Action details
|
Not available
|
2017 ACT-487
| 1 | 1. | | Action Item | CONTRACT CHANGE ORDER #2-RENEWABLE FUEL CREDIT MANAGEMENT FROM BIOCNG UTILIZATION-CONTRACTOR: ECOENGINEERS | approved | Pass |
Action details
|
Not available
|
2017 ACT-488
| 1 | 2. | | Action Item | CONTRACT CHANGE ORDER #3 RENEWABLE FUEL CREDIT MANAGEMENT FROM BIOCNG UTILIZATION-CONTRACTOR: ECOENGINEERS | approved | Pass |
Action details
|
Not available
|
2017 ACT-490
| 1 | 3. | | Action Item | CONTRACT CHANGE ORDER #3 CNG CARAGE RETROFIT-CONTRACTOR: ADVANCE BUILDING CORPORATION | approved | Pass |
Action details
|
Not available
|
2017 ACT-491
| 1 | 4. | | Action Item | CONTRACT CHANGE ORDER #4 CNG GARAGE RETROFIT-CONTRACTOR: ADVANCE BUILDING CORPORATION | approved | Pass |
Action details
|
Not available
|
2017 ACT-494
| 1 | 5. | | Action Item | CONTRACT CHANGE ORDER #1 CFS HVAC CONSTRUCTION-CONTRACTOR: H & H INDUSTRIES, INC. | approved | Pass |
Action details
|
Not available
|
2017 ACT-495
| 1 | 6. | | Action Item | CONTRACT CHANGE ORDER #1 CFS-EXTERIOR JOINTS REPLACEMENT-CONTRACTOR: B&B QUALITY BUILDING RESTORATION OF WISCONSIN LLC | approved | Pass |
Action details
|
Not available
|
2017 ACT-496
| 1 | 7. | | Action Item | CONTRACT CHANGE ORDER #2 CFS-EXTERIOR JOINTS REPLACEMENT-CONTRACTOR: B&B QUALITY BUILDING RESTORATION OF WISCONSIN LLC | approved | Pass |
Action details
|
Not available
|
2017 ACT-497
| 1 | 8. | | Action Item | CONTRACT CHANGE ORDER #4 ARCHITECTURAL AND ENGINEERING DESIGN SERVICES AT SCHUMACHER FARM-CONTRACTOR: DIMENSION IV | approved | Pass |
Action details
|
Not available
|
2017 ACT-499
| 1 | 9. | | Action Item | CONTRACT CHANGE ORDER #1 A/E DESIGN SERVICES FOR PSB CNG RETROFIT-CONTRACTOR: DORSCHNER ASSOCIATES AND ENGINEERING 370 | approved | Pass |
Action details
|
Not available
|
2017 ACT-500
| 1 | 10. | | Action Item | CONTRACT CHANGE ORDER #11 INDIAN LAKE RESTROOM & SITE IMPROVEMENTS-CONTRACTOR: MCKEE ASSOCIATES | approved | Pass |
Action details
|
Not available
|
2017 ACT-505
| 1 | 11. | | Action Item | CONTRACT CHANGE ORDER #1 CCB ELEVATOR MODERNIZATION NO. 1-4 (CREDIT)-CONTRACTOR: SCHUMACHER ELEVATOR COMPANY | approved | Pass |
Action details
|
Not available
|
2017 ACT-506
| 1 | 12. | | Action Item | CONTRACT CHANGE ORDER #3 PROFESSIONAL ENGINEERING SERVICES FOR BIOGAS FACILITY-CONTRACTOR: CORNERSTONE ENVIRONMENTAL GROUP, LLC. | approved | Pass |
Action details
|
Not available
|